RLH61- Restoration Begins

JUNE 2004

Removal of panels in key places was one of the first jobs to see how bad the frame work was.

The rear quarter was, as expected, rotten and further removal of panels leading forwards were all in similar condition.

In every nook and cranny water had been getting in, where this had then frozen and expanded this had led to distortion of the frame and panels, which in turn let in more water.


JULY 2004

It became apparent that to do the vehicle justice the only option was to largely rebuild much of the bus. As the panels and then the window frames were removed the level of deterioration became more obvious. Fuel tanks, battery trays, wheel arches and window pans all had to come out.

Most of the stuff removed was little more than junk and was of no use.

It became necessary to take pictures of the bus as parts were removed to ensure that when it was put back together it would be authentic.

The idea had originally been to have RLH 61 ready for January 13th but with the scale of work to be done this instantly looked unlikely.



AUGUST 2004

As the roof was largely holding the bus together, on removal of the side panels it was not possible to remove it until the commencement of the re-framing. Even when some of the side frames had been put back it was impossible to remove all the roof panels as the bus was bowing in places, so more work was needed to stabilise the vehicle before the last panels could be removed. Alas a virus that wiped our computer has led to a lack of surviving shots of this particular period of the rebuild


OCTOBER 2004

By the autumn, RLH 61 was still at the very early stages of rebuild, as can be seen from this views. This photo shows all the new wooden framework before the start of replacing the upper panel work. The cab had many issues but the first was to replace the upper deck floor, re-skin the cab roof and remove all the old electrics which were all defunct. Meanwhile the platform was removed and the risers replaced.
   
The lower deck saloon seen here, shows the bus without window pans and following removal of seats and early preparation of the ceiling.


NOVEMBER 2004

With the wooden frame completed the bus was solid enough to be lifted to gain a look at the underneath and also endeavour to get the engine started. With the fuel tanks being of no use the bus was connected to a bucket of diesel for her first run up!
   
Without the staircase in position it’s possible to see straight through the bus. This view perhaps best demonstrates the level of rebuild that has taken place with each and every piece of wood going in being treated so that the bus will actually be better than new!!


DECEMBER 2004

Whilst the interior could not be properly started until the window pans were in, the rear end exterior had no such restrictions and re-panelling commenced quickly. The emergency exit upstairs was another problem area and had to be removed and rebuilt separately, whilst the interior walls around the staircase were also re-skinned.

The cant rail was reskinned as was the front wings and bulkhead. The missing panels on the nearside shot are for the removable inspection panels that had to be rebuilt from scratch using the rotten ones as patterns.